To:      Governance and Audit Committee

26th January 2022

                                                                                                                                                      

 

Internal Audit Update

Head of Audit and Risk Management

1          Purpose of Report

1.1       This report presents the update on progress on the annual Internal Audit Plan.

2          Recommendations

2.1       To note the update on progress on the Internal Audit Plan for 2021/22.

3          Reasons for Recommendations

3.1       To ensure the Council complies with statutory requirements for internal audit.

4          Alternative Options Considered

4.1       There are no alternatives.

5          Supporting Information

Internal Audit

5.1       Delivery of the Council’s internal audit services in 2021/22 is being delivered as follows:

·         TIAA Ltd who will undertake IT audit;

·         Farsight Consulting who will audit schools,

·         Wokingham Council’s Business Assurance team delivering internal audit services under a S113 agreement;

·         Temporary senior auditors; and

·         two permanent in-house senior auditors who joined us in the summer of 2021.

5.2       Progress against the 2021/22 Internal Audit Plan is set out in Appendix 1. There has been some delay in progressing the 21/22 Audit Plan as a backlog of 20/21 audits deferred to late qtr 4 or early qtr 1 of 21/22 at management request had first to be cleared, schools scheduled to be audited were not prepared to have audits undertaken until the autumn and the new senior auditors were not able to join us until July and August. One of the senior auditors has now had to resign for health reasons. This is having a knock on effect and hence additional temporary senior auditor support is now being brought in and some audits have been deferred to 22/23.

6          Consultation and Other Considerations

Legal Advice

6.1       There are no specific legal implications arising from the recommendations in this Report.

Financial Advice

6.2       There are no financial implications arising from this report.

Equalities Impact Assessment

6.3       Not applicable.

Strategic Risk Management Issues

6.4       A robust internal audit service is essential for ensuring proper processes are in place for effective control.

Background Papers

Internal Audit Plan 2021/22

Internal Audit Charter

 

Contact for further information

Sally Hendrick, Head of Audit and Risk Management - 01344 352092


 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Sally Hendrick

Head of Audit and Risk Management

Sally.hendrick@bracknell-forest.gov.uk

01344 352092


 

1.1       The Council is required under the Accounts and Audit (Amendment) (England) Regulations to “maintain an adequate and effective system of internal audit of its accounting records and of its systems of internal control in accordance with the proper practices in relation to internal control.” This report summarises the activities of Internal Audit for the period April to December 2021 drawing together progress on the Annual Internal Audit Plan, risk management and other activities carried out by Internal Audit.

 

 

 

2.1       The basic approach adopted by Internal Audit falls broadly into four types of audit:

·             System reviews provide assurance that the system of control in all activities undertaken by the Council is appropriate and adequately protects the Council’s interests. 

·             Regularity (financial) checking helps ensure that the accounts maintained by the Council accurately reflect the business transacted during the year.  It also contributes directly towards the external auditor’s audit of the annual accounts. 

·             Computer/IT audits, carried out by specialist audit staff, provide assurance that an adequate level of control exists over the provision and use of computing facilities

·             Certification as required by relevant Government departments that grant monies have been spent in accordance with grant terms and conditions.

 

2.2       Recommendations are made after individual audits, leading to an overall assurance opinion for the system or establishment under review and building into an overall annual assurance opinion on the Council’s operations called the Head of Internal Audit Annual Opinion.  The different categories of recommendation and assurance opinions are set out in the following tables.

 

2.3       Since 1st April 2019 we have been categorising our audit opinions according to our assessment of the controls in place and the level of compliance with these controls as follows::

 

 

Good - There is a sound system of internal control designed to achieve the objectives of the system/process and manage the risks to the achievement of objectives and this is being complied with. Recommendations will only be of low priority.

 

Adequate - there is basically a sound system of control but there are some areas of minor weakness and/or some areas of non- compliance which put the system/process objectives at risk. Recommendations will only be low or moderate in priority.

 

Partial - there are areas of weakness and/or non- compliance with control which put the system/process objectives at risk and undermine the system’s overall integrity.  Recommendations may include major recommendations but could only include critical priority recommendations if mitigated by significant strengths elsewhere.

 

Inadequate - controls are weak across a number areas of the control environment and/or not complied with putting the system/process objectives at significant risk. Recommendations will include major and/or critical recommendations

 

None - There is no control framework in place and management is inadequate leaving the system open to risk of significant error or fraud.

 

2.4       We categorise our recommendations according to their level of priority as set out below:

 

 

Critical - Critical and urgent in that failure to address the risk could lead to factors such as significant financial loss, significant fraud, serious safeguarding breach, critical loss of service, critical information loss, failure of major projects, intense political or media scrutiny. Remedial action must be taken immediately.

 

Major - failure to address issues identified by the audit could have significant impact such as high financial loss, safeguarding breach, significant disruption to services, major information loss, significant reputational damage or adverse scrutiny by external agencies. Remedial action to be taken urgently.

 

Moderate - failure to address issues identified by the audit could lead to moderate risk factors materialising such as medium financial loss, fraud, short term disruption to non-core activities, scrutiny by internal committees, limited reputational damage from unfavourable media coverage. Prompt specific remedial should be taken.

 

Low - failure to address issues identified by the audit could lead to low level risks materialising such as minor errors in system operations or processes, minor delays without impact on service or small financial loss. Remedial action is required.

 

 

3.1       The Annual Internal Audit Plan for 2021/22 was considered and approved by the Governance and Audit Committee on 24th March 2021. The delivery of the individual audits during 2021/22 is being undertaken by

·         TIAA Ltd who will undertake IT audit;

·         Farsight Consulting who will audit schools,

·         Wokingham Council’s Business Assurance team delivering internal audit services under a S113 agreement;

·         Temporary senior auditors; and

·         two permanent in-house senior auditors who joined us in the summer of 2021.

3.2       There has been some delay in progressing the 21/22 Audit Plan as a backlog of 20/21 audits deferred to late qtr 4 or early qtr 1 of 21/22 at management request had first to be cleared, schools scheduled to be audited were not prepared to have audits undertaken until the autumn. Good progress has now been made on school audits. The two new senior auditors were not able to join us until July and August and one has now resigned for health reasons. This is putting additional pressure on delivery and hence some further audits have now been deferred to 22/23. One new temporary senior had already been appointed to address backlog and a further temp is now being recruited.

 

3.3       Between April to December 2021, 7 grant audits and 20 reports/memos were finalised, 3 reports/memos were issued in draft awaiting management responses, 4 were issued for discussion, 3 reports were at quality review stage and 10 audits were work in progress.

 

3.4       Details on the status and outcome of all audits are attached at Appendix A. A summary of the outcome of finalised and audits with reports issued in draft are set out below.

 

2021/22 ASSURANCE

LEVELS

NUMBER OF AUDITS

TO DATE

 

2020/21

ASSURANCE

LEVELS

NUMBER OF AUDITS

Good

2

 

Good

4

Adequate

10

 

Adequate

15

Partial

5

 

Partial

10

Inadequate

2

 

Inadequate

0

No assurance

0

 

No assurance

0

Total for Audits with an Opinion

19

 

Total for Audits with an Opinion

29

Memos and reports with Major Recommendation and no Opinion

3

 

Memos and reports with Major Recommendation and no Opinion

4

Other Follow Up Memos/ Reports with no Opinion

2

 

Other Follow Up Memos/ Reports with no Opinion

3

Total Audits

24

 

Total Audits

36

Grant Certifications/Submissions

7

 

Grant Certifications

7

Overall Total

31

 

Overall Total

43

 

 

 

Identified High Priority Control Issues

 

3.5       Audits which have identified high priority recommendations will generally be revisited in 2022/23, to ensure successful implementation of agreed recommendations.  The audits where major and critical recommendations have been raised are set out below:

 

 


 

AUDITS WHERE HIGH PRIORITY ISSUES HAVE BEEN IDENTIFIED SINCE THE LAST UPDATE IN THE INTERNAL AUDIT 20/21 ANNUAL REPORT IN SEPTEMBER 2021

·      parenting assessments (20/21 AUDIT)

The audit was requested by the Assistant Director: Children’s Social Care to establish if there was any validity in concerns that she had that procedures may not be being consistently applied. Three major recommendations were raised relating to non-compliance with key steps in the processes, the lack of performance & quality checks and the gaps in knowledge within the service. A new management team is now in place which will address weaknesses in compliance and supervisory oversight and address gaps in knowledge and understanding of processes.

 

ASSURANCE OPINION: INADEQUATE

·      GREEN HOMES GRANTS

This audit was requested by the Executive Director: Delivery as it was a significant expenditure stream that had been transferred from another Directorate and there had been gaps at manager level during the period that the grants were being given which could potentially have increased risk. The audit established that there were weaknesses in controls. Eight major recommendations were raised on resourcing, the promotion of the scheme, procurement processes, lack of independence in the assessment process, weaknesses in the process for agreeing quotes with contractors, weak control over payments for works, GDPR weaknesses and concerns around records maintained and reporting on grant spend. There is now a robust management structure in place, action will be taken to ensure that appropriate administrative support would be put in place for any future tranches of grant funding, clarification has been sought on procurement requirements and guidance has been provided on expenditure controls.

 

ASSURANCE OPINION: INADEQUATE

·      COMPLAINTS PROCESS

Four major recommendations were raised in respect of resourcing complex complaints; completeness of records, monitoring of complaints and actions for improvement and corporate reporting. An action plan has been developed by senior managers which includes creating a new Complaints Officer post to provide specialist support. Actions are already progressing and will be overseen by the Corporate Management Team.

ASSURANCE OPINION: PARTIAL

·      E+ cARD

Two major recommendations were raised relating to the absence of both a Data Protection Impact Assessment and data flow mapping for the interface systems.

ASSURANCE OPINION: PARTIAL

·      LARCHWOOD

Three major recommendations were raised on pre-employment checks for agency workers, expenditure controls and imprest reconciliations.

ASSURANCE OPINION: PARTIAL

·      PERMANENCY PLANNING

Permanency Planning processes assess the most effective and viable options for a permanency plan for a child or young person. This was an advisory review requested by the Assistant Director: Children’s Social Care to establish if there was any validity in concerns that she had that these processes may not be being consistently applied. Two major observations were raised by Internal Audit in relation to meetings records and management information on compliance with statutory timeframes for meetings that will be taken forward by the management team.

ADVISORY REVIEW WITH NO AUDIT OPINION BUT MAJOR RECOMMENDATION RAISED

·      SERVICES TO SCHOOLS

Three major recommendations have been raised. These relate to costing of services and overheads to ensure accurate recharging and assess viability, systems integration procedures and resourcing of systems support and systems finance administration support.

 

ASSURANCE OPINION: PARTIAL

 

In addition, some major recommendations have been raised at a number of audits such as climate change which though considered significant for management did not prevent us from concluding that controls were adequate.  A major recommendation was raised at all school audits undertaken to date in respect to medium term budget forecasts predicting deficits over the next 3 years. Whilst this has not resulted in itself in a partial or inadequate opinion this is something governing bodies should continue to monitor.

 

 

Update of Previous Audits with High Priority Recommendations

 

3.6       Since April 2021, we have followed up one audit from 2020/21 where significant weaknesses had been identified (reactive maintenance). The Head of Audit and Risk Management can report that issues previously identified have been addressed.

 

 

External Quality Assessment and Quality Assurance and Improvement Programme

 

3.7       Under mandatory Public Sector Internal Audit Standards our internal audit service has to be externally assessed every 5 years. This is now due and is being undertaken by CIPFA in April 2022.

 

3.8       As shown below, to date all completed client questionnaires received for 2021/22 have shown the auditees to be satisfied with the service.  In 77%f cases internal audit delivered the first draft report within 15 days of the exit meeting.

 

 

Client Questionnaires

Draft Report /Memo Produced within 15 Days of Exit meeting

 

Received

Satisfactory

1st April to 31st August 2021

6

100%

77%

2020/21

9

89%

60%

 

 

 

4.1       It is still too early in the financial year to make a reliable assessment on the direction of travel of the control environment. Progress to improve the control environment will be monitored quarterly based on the outcome of the audits undertaken and in particular identifying whether agreed management actions for areas previously found to have significant control weaknesses have been implemented as this has been a key factor in the Head of Audit and Risk Management’s annual opinion on the control environment for the last 3 years.

 

 

 

5.1       The Strategic Risk Register has already been reviewed three times by the Strategic Risk Management Group (SRMG) and once by the Corporate Management Team. Directorate risk registers continue to be updated quarterly.

 

 


APPENDIX 1

2020/21 INTERNAL AUDIT PLAN OUTCOMES NOT PREVIOUSLY REPORTED

 

*Key indicator- Draft report issued within 15 days of exit meeting

“D”- deferred at management request from 20/21 to 21/22

 

AUDIT

Start Date

Date of Draft Report

*Key Indicator Met

Assurance Level

Recommendation

Priority

Status

 

 

 

 

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

 

Security camera controls

2/3/21

20/8/21

P

 

 

P

 

 

 

3

2

Finalised

Parenting Assessments

11/1/21

9/6/21

P

 

 

 

P

 

 

3

3

Finalised

Foster Panels Compliance

May 2021

26/6/21

P

 

P

 

 

 

 

4

2

Finalised

Continuing Health Care

17/3/21

2/7/21

P

 

P

 

 

 

 

4

1

Finalised

 

 

2021/22 INTERNAL AUDIT PLAN

 

 

1.GOVERNANCE

 

AUDIT

Start Date

Date of Draft Report

Key Indicator Met*

Assurance Level

Recommendation

Priority

Status

 

 

 

 

Good

Adequate

Partial

inadequate

Critical

Major

Moderate

Low

 

Data indicators

 

 

 

 

 

 

 

 

 

 

 

Deferred to Qtr 1 of 22/23

Project management of O&S reviews and subsequent action plan implementation

 

 

 

 

 

 

 

 

 

 

 

Deferred to 22/23

Business Continuity

 

 

 

 

 

 

 

 

 

 

 

“D”

Audit deferred to qtr 1 of 22/23 as Business continuity project delayed due to COVID

Complaints Process

August 21

14/9/21

P

 

 

P

 

 

4

5

 

Finalised

Corporate Governance infrastructure –People only

 

 

 

 

 

 

 

 

 

 

 

Deferred to 22/23

E+ card- general control, IT controls and information governance arrangements with contractors

14/9/21

3/12/21

X

 

 

P

 

 

2

6

3

Revised draft report issued

Grant Reviews and Certifications

Bus Service Operator

21/9/21

21/9/21

P

N/A – Grant certification

Certified

Troubled Families

24/6/21

30/6/21

P

N/A – Memo to support PBR grant submission

 

 

 

 

Finalised

Troubled Families

27/9/21

30/9/21

P

N/A – Memo to support PBR grant submission

 

 

1

 

Finalised

Troubled Families- March 2022 submission

 

 

 

 

 

 

 

 

Qtr 4 audit

Green Homes Grants compliance audit

26/7/21

31/8/21

P

 

 

 

P

 

8

 

 

Finalised

COVID Restart grants

August 21

 

P

N/A- no opinion. Observations raised rather than recommendations

 

3

2

1

Finalised

COVID Additional Restrictions grants

August 21

01/12/21

P

N/A- no opinion. Observations raised rather than recommendations

 

3

2

2

Finalised

Pot Hole Fund

6/9/21

21/9/21

P

N/A – Grant certification

Certified

Local transport capital block funding (integrated transport and highways maintenance) 

6/9/21

21/9/21

P

N/A – Grant certification

Certified

Emergency Active Travel Fund

13/9/21

21/9/21

P

N/A – Grant certification

Certified

Active Travel Fund Tranche 2

13/9/21

21/9/21

P

N/A – Grant certification

Certified

 

2. COUNCIL WIDE

 

AUDIT

Start Date

Date of Draft Report

Key Indicator Met*

Assurance Level

Recommendation Priority

Status

 

 

 

 

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

 

Amazon  account

 

 

 

 

 

 

 

 

 

 

 

Asked to defer to 22/23 after the new Head of Procurement comes into post

Climate Change

 

July 2021

5/8/21

P

 

P

 

 

 

1

2

 

Finalised

Debt management

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

 

 

 

3. CORE FINANCIAL SYSTEMS

 

AUDIT

Start Date

Date of Draft Report

Key Indicator Met*

Assurance Level

Recommendation Priority

Status

 

 

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

 

Reconciliations

 

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

Staff establishment costs (Joint HR and Finance audit budgeted under OD, Transformation and HR)

1/12/21

 

 

 

 

 

 

 

 

 

 

Work in progress

Banking -advisory audit

 

 

 

 

 

 

 

 

 

 

 

Deferred to 22/23t

Council Tax and Business Rates

1/12/21

 

 

 

 

 

 

 

 

 

 

Work in progress

Creditors

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

Housing Benefit and Council Tax Reduction

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

 

4. IT AUDIT

 

IT AUDIT

Start

Date

Date of Draft Report

Key Indicator Me*

Assurance Level

 

 

 

 

Status

 

 

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

 

Transport routing

August 2021

27/10/21

X

 

P

 

 

 

 

2

2

Draft issued

Emergency Duty Service System

 

 

 

 

 

 

 

 

 

 

 

Deferred to qtr 4

Forestcare IT systems including telephony

 

 

 

 

 

 

 

 

 

 

 

Deferred to qtr 4 due to delays on the new system

Heath and Social Care ICT Care Systems Integration (Dependent upon Digital Strategy)

1/9/21

 

 

 

 

 

 

 

 

 

 

Work in progress

CORE waste management system

 

 

 

 

 

 

 

 

 

 

 

Cancelled

Agresso advisory review and support for upgrade and movement to the Cloud

 

 

 

 

 

 

 

 

 

 

 

Cancelled as not required by service area

Agresso (Follow up- major recommendations raised in 2019/20 and 2020/21)

1/12/21

 

 

 

 

 

 

 

 

 

 

Work in progress

Cyber Security – Incident Management and Resilience

 

 

 

 

 

 

 

 

 

 

 

Cancelled

Cyber liability (Follow up- partial assurance 2020/21)

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

DSPT NEW AUDIT

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

 

 


 

5. PLACE, PLANNING, AND REGENERATION

 

AUDIT

Start Date

Date of Draft Report

Key Indicator met

Assurance Level

Recommendation priority

Status

 

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

 

SANGs

May 2021

16/7/21

P

N/A – Advisory memo

 

 

 

1

“D”

Finalised

S106 – Use of the monies in compliance with development in the relevant geographic area

 

11/8/21

P

P

 

 

 

 

 

 

6

“D”

Finalised

Tree service

1/9/21

 

 

 

 

 

 

 

 

 

 

Received for review

Street lighting follow up (partial assurance opinion 2019/20)

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

Development Control

23/8/21

6/12/21

P

 

P

 

 

 

 

9

1

Draft issued

Building Control and land charges

29/9/21

29/11/21

P

 

P

 

 

 

 

6

1

Finalised

Public Health

 

 

 

 

 

 

 

 

 

 

 

Deferred to Qtr 1 of 22/23

 

T

6. CHIEF EXECUTIVE’S OFFICEcosts advisory review

 

AUDIT

Start Date

Date of Draft Report

Key Indicator met*

Assurance Level

Recommendation Priority

Status

 

 

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

 

Transformation support costs advisory review w

 

 

 

 

 

 

 

 

 

 

 

Deferred to Qtr 1 of 22/23

 

 

 


 

7. DELIVERY

 

AUDIT

Start Date

Date of Draft Report

Key Indicator met*

Assurance level

Recommendation Priority

Status

 

 

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

 

Public Protection Partnership (Follow up- partial assurance 2020/21)

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

Reactive Maintenance (Follow up- partial assurance 2020/21)

August 2021

27/8/21

P

N/A- Follow up memo. All recommendations addressed

 

 

 

 

Finalised

Commercial property (Follow up- partial assurance 2020/21)

 

 

 

 

 

 

 

 

 

 

 

Deferred to Qtr 1 of 22/23 as completion of actions expected June 22

Cemetery and Crematorium

12/7/21

15/9/21

X

 

P

 

 

 

 

10

1

“D”

Finalised

Everyone Active Covid support

 

30/6/21

P

P

 

 

 

 

 

 

 

Finalised

 

 

8. PEOPLE

 

AUDIT

 

Start Date

Date of Draft Report

Key Indicator Met*

Assurance levels

Recommendation Priority

Status

 

 

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

 

Transport in CTPLD- advisory review

 

 

 

 

 

 

 

 

 

 

 

“D”

Unable to progress planning due to staff sickness therefore defer to 22/23

Financial assessments

November 21

 

 

 

 

 

 

 

 

 

 

Received for review

Preparation for new Liberty Safeguard regulations – advisory piece

 

 

 

 

 

 

 

 

 

 

 

Audit deferred to 22/23 as new national guidance has still not been issued

Deputyships and appointees

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

Commissioning due diligence checks

 

 

 

 

 

 

 

 

 

 

 

These 2 audits have been deferred to 22/23 to free up resource to audit SEND

Children’s placements

 

 

 

 

 

 

 

 

 

 

 

Supervision- advisory review covering ASC and Mental Health

October 21

 

 

 

 

 

 

 

 

 

 

Work in progress

SEND targeted areas- NEW ADDITIONAL AUDIT

December 21

 

 

 

 

 

 

 

 

 

 

Work in progress

Breakthough (Follow up- partial assurance 2020/21)

 

 

 

 

 

 

 

 

 

 

 

Qtr 4 audit

Group supervision and Motivational interviews

 

 

 

 

 

 

 

 

 

 

 

Audit cancelled at request of service area

Equality, diversity and fair access to children’s social service

 

 

 

 

 

 

 

 

 

 

 

Deferred to 22/23

Permanency planning

August 2021

21/9/21

 

N/A memo issued on advisory with no opinion

 

2

1

 

Final memo issued

 

Post leaving Care

 

 

 

 

 

 

 

 

 

 

 

Deferred to 22/23

Larchwood

26/7/21

27/10/21

X

 

 

P

 

 

3

4

1

Draft report issued

 

Glenfield- mental health supported living

August 2021

8/10/21

P

 

P

 

 

 

 

3

 

“D”

Final report issued

 

Youth Offending service

 

 

 

 

 

 

 

 

 

 

 

Cancelled by service area

Forestcare

November 21

 

 

 

 

 

 

 

 

 

 

Work in progress

Disabled Facilities Grants-

 

 

 

 

 

 

 

 

 

 

 

Deferred to Qtr 1 of 22/23

Homelessness procurement advisory piece

12/10/21

 

 

 

 

 

 

 

 

 

 

Received for client-side review

Housing Management follow up

 

 

 

 

 

 

 

 

 

 

 

Deferred to Qtr 1 of 22/23

COVID Test and trace grants

 

 

 

 

 

 

 

 

 

 

 

Defer to 22/23 after grant programme has closed

Open Learning Centre

 

 

 

 

 

 

 

 

 

 

 

Deferred to late qtr 4 at service area request

Nursery provider support payments

 

 

 

 

 

 

 

 

 

 

 

Deferred to late qtr 4 at service area request

 

 

 

9. SCHOOLS

 

AUDIT

 

Start Date

Date of Draft Report

Key Indicator Met

Good

Adequate

Partial

Inadequate

Critical

Major

Moderate

Low

Status

 

 

 

 

 

 

 

 

 

 

 

 

 

School census

 

 

 

 

 

 

 

 

 

 

 

Work in progress

Services to schools- Can Do

12/8/21

7/12/21

X

 

 

P

 

 

3

9

 

Draft report issued

 

Free school meals

 

 

 

 

 

 

 

 

 

 

 

Work in progress

Fox Hill (follow up -Ltd 2017/18 and 2018/19)

 

 

 

 

 

 

 

 

 

 

 

“D”

Now deferred to qtr 4

The Pines

14/10/21

24/12/21

P

 

 

 

 

 

 

 

 

D”

Draft report issued for discussion

Woodenhill (follow up -Ltd 2018/19)

 

 

 

 

 

 

 

 

 

 

 

“D”

Qtr 4 audit

Ascot heath (reaudit-Ltd 2018/19)

1/11/21

24/12/21

 

 

 

 

 

 

 

 

 

“D” 

Work in progress

Sandhurst (follow up partial 19/20) Cancelled as becoming an academy

 

 

 

 

 

 

 

 

 

 

 

“D”

cancelled

Kennel Lane follow up

 

 

 

 

 

 

 

 

 

 

 

“D”

Qtr 3 audit

St Michael’s Easthampstead (follow up partial 19/20)

 

 

 

 

 

 

 

 

 

 

 

“D”

Qtr 3 audit

Whitegrove

7/6/21

29/7/21

X

 

P

 

 

 

1

4

 

“D”

Final issued

Binfield

22/11/21

17/12/21

P

 

 

 

 

 

 

 

 

“D”

Draft report issued for discussion

St Michael’s Sandhurst

11/10/21

22/12/21

x

 

P

 

 

 

1

3

1

D”

Draft report issued

Winkfield

4/10/21

20/12/21

X

 

 

 

 

 

 

 

 

D D”

Draft report issued for discussion

Owlsmoor

18/10/21

 

X

 

 

 

 

 

 

 

 

Draft report issued for discussion


 


APPENDIX 2

 

2020/21 AUDITS IDENTIFYING SIGNIFICANT ISSUES

AUDIT

RATING

CURRENT AUDIT STATUS

·      Debt Management  

PARTIAL

To be re-audited in Qtr 4

·      Management of Essential Car User Allowances and Mileage

PARTIAL

To be re-audited in Qtr 1 of 22/23

·      Public Protection Partnership

PARTIAL

To be followed up in Qtr 4

·      Management of Commercial Properties

 

PARTIAL

To be followed up in Qtr 3

·      Reactive Maintenance

PARTIAL

Followed up and all significant issues raised have been addressed

·      Cyber

PARTIAL

To be followed up in Qtr 4

·      Agresso IT System Follow Up

 

FOLLOW UP HENCE NO OPINION BUT MAJOR RECOMMENDATIONS RAISED

Re-audit in progress

·      Creditors

 

PARTIAL

To be re-audited in Qtr 4

·      Business Rates

 

·      Council Tax and council tax

 

BOTH PARTIAL

 

Re-audit in progress

·      Domiciliary Care Follow up

FOLLOW UP HENCE NO OPINION BUT MAJOR RECOMMENDATION STILL OUTSTANDING

To be re-audited in Qtr 1 of 22/23

·      Breakthrough

PARTIAL

To be followed up in Qtr 4

 

 


 

OTHER AUDITS AREAS WHERE SIGNIFICANT ISSUES IDENTIFIED PRE  20/21 WERE STILL OUSTANING AT 31/3/21

CURRENT AUDIT STATUS

·              Forestcare (Follow Up Memo. 2019/20 Also limited in 2017/18)

Re-audit in progress

·              Adult Social Care Pathway (Qtr 4 2017/18 Audit)

 

To be followed up in Qtr 1 of 21/22

·              Loans for Housing Rents and Deposits

 

To be followed up as part of the debt management audit in Qtr 4 of 21/22

·              Public Health

 

To be re-audited in Qtr 4

·              Disabled Facilities Grants

To be re-audited in Qtr 4

·              ICT Continuity Management

To be re-audited as part of business continuity in Qtr 1 of 22/23